Subfloor
construction including sill plate, floor joists and plywood
decking
-
Deck
construction for covered porches and open decks with rails
(no steps)
-
Log
wall installation and pre-drilling for wiring in first two courses
-
Second
floor girder beam and joist installation with applicable
wiring runs
-
Second
floor tongue & groove decking installation
-
Shed
dormer wall construction
-
House
ridge beam, rafter and collar tie construction
-
Gable
wall and gable dormer wall construction
-
Tongue
& groove decking installation, vapor barrier and wiring runs
(Premier Roof
System)
(For conventional roof -- OSB and felt installation)
-
Roof
insulation panels, OSB and felt installation (Premier Roof System)
(For conventional roof -- installation of roof insulation not a
part of dry-in process)
-
Porch
posts, plates and rafter construction
-
Tongue
& groove porch roof decking and felt
-
Insulation
board and log siding installation for gables and dormers
-
Exterior
doors and windows with exterior trim installation
-
Interior
stud wall construction and interior stars
-
Exterior
roof fascia installation
-
Subfloor
band siding installation